          50:02:01:17.  Time limits. Projects which are receiving state assistance must adhere to the following time limits. All times refer to days after the declaration of an emergency or disaster by the Governor.

Work

Initiation

Completion

Category

of Work

of Work

 

 

 

(1) Debris clearance

30 days

180 days

(2) Emergency measures

30 days

180 days

(3) Permanent work

 

18 months

          The time limits imposed by ยงยง 50:02:01:15 and 50:02:01:16 and this section may be extended by the director of the Division of Emergency Management for up to six months if requested and justified in writing by the applicant. Justification must be based on extenuating circumstances beyond the control of the applicant.

          Source: 20 SDR 189, effective May 15, 1994.

          General Authority:SDCL 33-15-24.8.

          Law Implemented:SDCL 33-15-24.8.