74:55:01:04. Date of application for new wells. Operators
of a new injection well shall submit a complete application at least 270 days
before the date construction is expected to begin unless the new well is
covered by an area permit.
Source:
8 SDR 71, effective December 24, 1981; 13 SDR 129, 13 SDR 141, effective
July 1, 1987; transferred from § 74:03:11:04, July 1, 1996; 34 SDR
279, effective May 12, 2008.
General
Authority: SDCL 34A-2-93(15).
Law
Implemented: SDCL 34A-2-28.
Online Archived History: