74:55:01:21. Compliance schedule for permit conditions. A
compliance schedule for permit conditions shall be set by the secretary not to
exceed three years following the effective date of the permit. If the
compliance schedule exceeds one year, then interim requirements and completion
dates, not to exceed one year, shall be incorporated into the compliance
schedule and permits. No later than 14 days following each interim and final
date the permittee shall notify the secretary of compliance or noncompliance.
Source:
8 SDR 71, effective December 24, 1981; 13 SDR 129, 13 SDR 141, effective
July 1, 1987; transferred from § 74:03:11:21, July 1, 1996; 34 SDR
279, effective May 12, 2008.
General
Authority: SDCL 34A-2-93(15).
Law
Implemented: SDCL 34A-2-39.