State of South Dakota
|
NINETY-FOURTH SESSION
LEGISLATIVE ASSEMBLY, 2019
|
400B0363
|
HOUSE ENGROSSED NO. SB 15 - 3/7/2019
|
This bill has been extensively amended (hoghoused) and may no longer be consistent
with the original intention of the sponsor.
Introduced by: The Committee on Commerce and Energy at the request of the Public
Utilities Commission
|
FOR AN ACT ENTITLED, An Act to define solar energy facilities, establish certain provisions
regarding solar energy permits, and revise the procedures by which the Public Utilities
Commission processes facility permits.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF SOUTH DAKOTA:
Section 1. That § 49-41B-2 be amended to read:
49-41B-2. Terms as used in this chapter mean:
(1) "AC/DC conversion facility," an asynchronous AC to DC to AC tie that is directly
connected to a transmission facility or a facility that connects an AC transmission
facility with a DC transmission facility or vice versa;
(2) "Associated facilities," facilities which include aqueducts, diversion dams,
transmission substations, storage ponds, reservoirs, or cooling ponds;
(3) "Carbon dioxide," a fluid that consists of more than ninety percent carbon dioxide
molecules compressed in a supercritical state;
(4) "Commission," the Public Utilities Commission;
(5) "Construction," any clearing of land, excavation, or other action that would affect the
environment of the site for each land or rights of way upon or over which a facility
may be constructed or modified, but not including activities incident to preliminary
engineering or environmental studies. This term includes modifications to facilities
as defined in § 49-41B-2.2;
(6) "Energy conversion facility," any new facility, or facility expansion, designed for or
capable of generation of one hundred megawatts or more of electricity, but does not
include any wind or solar energy facilities;
(7) "Facility," any energy conversion facility, AC/DC conversion facility, transmission
facility, solar energy facility, or wind energy facility, and associated facilities;
(8) "Permit," the permit issued by the commission under this chapter required for the
construction and operation of a facility;
(9) "Person," an individual, partnership, limited liability company, joint venture, private
or public corporation, association, firm, public service company, cooperative,
political subdivision, municipal corporation, government agency, public utility
district, or any other public or private entity, however organized;
(10) "Siting area," that area within ten miles in any direction of a proposed energy
conversion facility, AC/DC conversion facility, or which is determined by the
commission to be affected by a proposed energy conversion facility;
(11) "Trans-state transmission facility," an electric transmission line and its associated
facilities which originates outside the State of South Dakota, crosses this state and
terminates outside the State of South Dakota; and which transmission line and
associated facilities delivers electric power and energy of twenty-five percent or less
of the design capacity of such line and facilities for use in the State of South Dakota;
(12) "Utility," any person engaged in and controlling the generation or transmission of
electric energy and gas or liquid transmission facilities as defined by § 49-41B-2.1;
(13) "Wind energy facility," a new facility, or facility expansion, consisting of a
commonly managed integrated system of towers, wind turbine generators with
blades, power collection systems, and electric interconnection systems, that converts
wind movement into electricity and that is designed for or capable of generation of
one hundred megawatts or more of electricity. A wind energy facility expansion
includes the addition of new wind turbines, designed for or capable of generating
twenty-five megawatts or more of electricity, which are to be managed in common
and integrated with existing turbines and the combined megawatt capability of the
existing and new turbines is one hundred megawatts or more of electricity. The
number of megawatts generated by a wind energy facility is determined by adding the
nameplate power generation capability of each wind turbine;
(14) "Solar energy facility," a new facility, or facility expansion, consisting of a
commonly managed integrated system of solar panels, power collection systems,
electric interconnection systems, and associated facilities, that converts solar energy
into electricity and is designed for or capable of generating one hundred megawatts
AC or more of electricity. A facility expansion includes the addition of new solar
panels, designed for or capable of generating twenty-five megawatts AC or more of
electricity, that are to be managed in common and integrated with existing solar
panels, and the combined megawatt capability of the existing and new solar panels
is one hundred megawatts AC or more of electricity.
Section 2. That § 49-41B-35 be amended to read:
49-41B-35. To implement the provisions of this chapter regarding facilities, the commission
shall promulgate rules pursuant to chapter 1-26. Rules may be adopted by the commission:
(1) To establish the information requirements and procedures that every utility must
follow when filing plans with the commission regarding its proposed and existing
facilities;
(2) To establish procedures for utilities to follow when filing an application for a permit
to construct a facility, and the information required to be included in the application;
and
(3) To require bonds, guarantees, insurance, or other requirements to provide funding for
the decommissioning and removal of a
solar or wind energy facility.
Section 3. That § 49-41B-36 be amended to read:
49-41B-36. Nothing in this chapter is a delegation to the commission of the authority to
route a transmission facility, or to designate or mandate location of an energy conversion
facility, AC/DC conversion facility,
solar energy facility, or wind energy facility.
Section 4. That § 49-41B-5.2 be amended to read:
49-41B-5.2.
The Within thirty days following the filing of an application for permit, the
applicant shall notify, in writing, the owner of record of any land that is located within one-half
mile of the proposed site where the facility is to be constructed. For purposes of this section, the
owner of record is limited to the owner designated to receive the property tax bill sent by the
county treasurer. The notice shall be mailed by certified mail.
The applicant shall also publish
a notice of the proposed facility. Notification shall be published in the official newspaper of
each county in which the proposed site is located. The notice shall be published at least once
each week for at least two consecutive weeks. The notice shall contain a description of the
nature and location of the facility. Any notification required by this section shall state the date,
time, and location of the public
hearing and shall be made no later than thirty days prior to the
date of the public hearing. However, the second published notice shall be made no later than
twenty days prior to the date of the public hearing input meeting. The applicant shall also file
a copy of the application with the auditor of each county in which the proposed facility will be
located.
Section 5. That § 49-41B-15 be amended to read:
49-41B-15. Within thirty days following receipt of an application for a permit, the
commission shall:
(1) Schedule a public hearing input meeting;
(2) Notify the applicant of the hearing public input meeting; and
(3) Serve notice of the application and hearing public input meeting upon the governing
bodies of the counties and municipalities totally or partially within the area of the
proposed facility;
(4) Publish a notice of the time, place, and purpose of the public hearing in at least one
newspaper of general circulation in counties totally or partially within the area of the
proposed facility; and
(5) File a copy of the application with the auditor of the county or counties in which the
proposed facility will be constructed.
Section 6. That § 49-41B-16 be amended to read:
49-41B-16.
Within thirty days after public notice is given, the Public Utilities Commission
The commission shall hold
any public
hearings input meeting as close as
practicable practical
to the proposed facility.
The commission shall publish a notice of the time, place, and purpose
of any public input meeting three times in at least one newspaper of general circulation in any
county totally or partially within the area of the proposed facility. Each notification required in
this section shall state the date, time, and place of the public input meeting. The first notice shall
be published no later than thirty days prior to the date of the public input meeting. The second
notice shall be published no later than twenty days prior to the date of the public input meeting.
The third notice shall be published no later than two days prior to the date of the public input
meeting.
Section 7. That § 49-41B-17 be amended to read:
49-41B-17. The parties to a proceeding under this chapter unless otherwise provided
include:
(1) The Public Utilities Commission and applicant commission staff;
(2) The applicant;
(3) Each municipality, county and governmental agency in the area where the facility is
proposed to be sited, if timely application therefore is made as determined by the
commission pursuant to rule; and
(3)(4) Any person residing in the area where the facility is proposed to be sited,
any
nonprofit organization, formed in whole or in part to promote conservation or natural
beauty, to protect the environment, personal health or other biological values, to
preserve historical sites, to promote consumer interests, represent commercial and
industrial groups, or to promote the orderly development of the areas in which the
facility is to be sited or any
directly interested person, if timely application therefore
is made as determined by the commission pursuant to rule.
A statement filed by a
party to a permit proceeding shall become part of the record and shall be available
to the public. An application for party status in a proceeding under this chapter must
contain a detailed statement of the interests and reasons prompting the application.
Section 8. That § 49-41B-22 be amended to read:
49-41B-22. The applicant has the burden of proof to establish
by a preponderance of the
evidence that:
(1) The proposed facility will comply with all applicable laws and rules;
(2) The facility will not pose a threat of serious injury to the environment nor to the
social and economic condition of inhabitants or expected inhabitants in the siting
area. An applicant for an electric transmission line, a solar energy facility, or a wind
energy facility that holds a conditional use permit from the applicable local units of
government is determined not to threaten the social and economic condition of
inhabitants or expected inhabitants in the siting area;
(3) The facility will not substantially impair the health, safety or welfare of the
inhabitants; and
(4) The facility will not unduly interfere with the orderly development of the region with
due consideration having been given the views of governing bodies of affected local
units of government. An applicant for an electric transmission line, a solar energy
facility, or a wind energy facility that holds a conditional use permit from the
applicable local units of government is in compliance with this subdivision.
Section 9. That § 49-41B-25 be amended to read:
49-41B-25. Within six nine months of receipt of the initial application for a permit for the
construction of a wind energy facility or solar energy facility, the commission shall make
complete findings, and render a decision, regarding whether a permit should be granted, denied,
or granted upon such terms, conditions, or modifications of the construction, operation, or
maintenance as the commission deems determines are appropriate. In its the decision, the
commission must shall find that the construction of the facility meets all requirements of this
chapter. Notice of the commission's decision shall be given to the applicant and to parties to the
hearing within ten days following the decision.
Section 10. That chapter 49-41B be amended by adding a NEW SECTION to read:
Upon request of the applicant, the commission may extend the deadlines for commission
action established in §§ 49-41B-24 and 49-41B-25.
Section 11. That chapter 49-41B be amended by adding a NEW SECTION to read:
The commission shall accept public comments on all applications filed under this chapter.
Comments may be collected and forwarded to the commission on behalf of the commentators.
The commission shall publish on the commission's website all comments that are accepted
pursuant to this section, and may publish substantially similar comments by publishing one of
the comments and attributing the content of the comment to a number of persons.
Section 12. That chapter 49-41B be amended by adding a NEW SECTION to read:
A party to a proceeding under this chapter as provided in § 49-41B-17 is entitled to a