20:10:36:01. Scope and applicability. The rules in this
chapter govern the interconnection of small generator facilities in South
Dakota with an electric nameplate capacity of ten megawatts or less to the
electric distribution system of a public utility. The rules do not apply to
small generator facilities subject to the interconnection requirements of FERC
or a regional transmission organization. If a generation facility has an
electric nameplate capacity of more than ten megawatts that may be subject to
the commission's interconnection jurisdiction, this chapter may be used as the
basis for the interconnection process.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.