20:10:36:24. Interconnection facilities deposit. The
public utility may require a deposit of not more than 50% of the estimated
costs for interconnection facilities necessary to complete an interconnection
to the EDS. However, the deposit may not exceed $10,000 for small generator
facilities proposing to interconnect 500 kilowatts or less. The deposit shall
be paid in advance by the applicant for facilities necessary to complete an
interconnection to the EDS.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.
Online Archived History:
There are currently no online archives for this rule.