20:10:36:31. Tier 1 interconnection requirements. The
public utility shall use the tier 1 review procedures for a small generator
facility application that meets the following requirements:
(1) The proposed facility is inverter-based;
(2) The proposed facility has an electric
nameplate capacity of 10 kilowatts or less;
(3) The proposed facility will use lab tested
equipment only; and
(4) The proposed point of interconnection is not
to a transmission line.
A public utility may not impose additional requirements to
a tier 1 interconnection application.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.