MyLRC +
Administrative Rules
Rule 20:10:36:34 Tier 1 application completion.

          20:10:36:34.  Tier 1 application completion. The tier 1 interconnection process is complete when:

 

          (1)  The application has passed the tier 1 screening criteria;

          (2)  The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;

          (3)  The witness test, if conducted by the public utility, is successful;

          (4)  The parties execute a certificate of completion; and

          (5)  An interconnection agreement has been executed.

 

          Source: 35 SDR 305, effective July 1, 2009.

          General Authority: SDCL 49-34A-27, 49-34A-93.

          Law Implemented: SDCL 49-34A-27, 49-34A-93.

 

Online Archived History: