20:10:36:34. Tier 1 application completion. The tier 1
interconnection process is complete when:
(1) The application has passed the tier 1
screening criteria;
(2) The small generator facility installation is
approved by an electric code inspector with jurisdiction over the
interconnection;
(3) The witness test, if conducted by the public
utility, is successful;
(4) The parties execute a certificate of
completion; and
(5) An interconnection agreement has been
executed.