20:10:36:39. Failure
to meet tier 2 criteria -- Minor modifications. If the small generator
facility fails to meet one or more of the tier 2 screening criteria, but the
public utility determines that the small generator facility could be
interconnected safely if minor modifications to the EDS were made, the public
utility shall offer the applicant a non-binding, good faith estimate of the
costs of the proposed minor modifications and proceed with the minor
modifications if authorized by the applicant.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.