20:10:36:40. Tier 2 application completion. The tier 2
interconnection process is complete when:
(1) All tier 2 screening criteria are satisfied
and any minor EDS modifications are implemented;
(2) The small generator facility installation is
approved by an electric code inspector with jurisdiction over the
interconnection;
(3) The witness test, if conducted by the public
utility, is successful;
(4) The parties execute a certificate of
completion; and
(5) An interconnecting agreement has been executed.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.