20:10:36:41. Tier 2 application denial. If the small
generator facility's tier 2 application is not
approved, the applicant may submit a new application, including the difference
in the application fee or deposit, for consideration under tier 3 or tier 4
procedures without losing its original queue position. The new application must
be submitted within 15 business days of notice that the application was not
approved. If requested, the public utility shall provide a written explanation
of why the application was not approved.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.