20:10:36:47. Tier 3 interconnection approval. The public
utility shall approve the tier 3 application if the public utility determines
that the application:
(1) Passes the tier 3 screening criteria; or
(2) Fails one or more of the tier 3 screening criteria,
or does not meet every approval requirement, but the public utility determines
that the small generator facility can be interconnected safely and reliably
after making modifications and the public utility has received authorization
from the applicant to implement the minor modifications.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.