20:10:36:49. Tier 3 interconnection completion. The tier
3 application process is complete when:
(1) All tier 3 screening criteria are satisfied
and any minor modifications to the EDS that may have been identified are
implemented;
(2) The small generator facility installation is
approved by an electric code inspector with jurisdiction over the
interconnection;
(3) There is a successful completion of the
witness test, if required;
(4) The parties execute a certificate of
completion; and
(5) An interconnection agreement has been
executed.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.