20:10:36:56. Optional tier 4 interconnection system impact
study results meeting. The public utility shall contact the applicant to
schedule an optional tier 4 interconnection system impact study results meeting
to review the interconnection system impact study report and discuss the
identified interconnection facilities and system upgrades. The parties may also
mutually agree to adjust the study timeline determined at the scoping meeting
based upon the interconnection system impact study results.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.