20:10:36:59. Tier 4 interconnection approval. Upon
completion of the tier 4 interconnection facilities study and execution of an
agreement between the parties detailing progress billing, final billing,
payment schedules, and deposit, the public utility shall approve the
application.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.
Online Archived History:
There are currently no online archives for this rule.