Rule 20:10:36:61 Tier 4 interconnection completion.

          20:10:36:61.  Tier 4 interconnection completion. The tier 4 interconnection is considered complete when:

 

          (1)  All interconnection facilities and system upgrades are completed and operational;

          (2)  The small generator facility installation is inspected and approved by the electric code inspector with jurisdiction over the interconnection;

          (3)  There is a successful completion of the witness test, if conducted by a public utility;

          (4)  The parties execute a certificate of completion; and

          (5)  The parties execute an interconnection agreement.

 

          Source: 35 SDR 305, effective July 1, 2009.

          General Authority: SDCL 49-34A-27, 49-34A-93.

          Law Implemented: SDCL 49-34A-27, 49-34A-93.

 