20:10:36:71. Termination. The interconnection customer
may terminate the interconnection at any time by giving the public utility 20
business days' written notice.
Upon termination of the interconnection, any small
generator facility interconnection equipment must be disconnected from the
public utility's EDS at the interconnection customer's expense. The termination
of the interconnection does not relieve either party of its liabilities and
obligations owed or continuing at the time of the termination.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.