Rule 70:10:01:09 Process for application approval.

          70:10:01:09.  Process for application approval. Prior to approving a permit, the department shall send a copy of the complete permit application to all other permittees of the utility corridor. The department shall accept written comments concerning the approval or denial of the permit application for thirty days thereafter.

 

          Source: 32 SDR 32, effective August 30, 2005.

          General Authority: SDCL 31-19-1.1.

          Law Implemented: SDCL 31-19-1.1.

 

Online Archived History: