24:52:13:01. Applications for project review -- Requirements. Applicants seeking project review shall, at a minimum, provide the following information:
(1) The name of the applicant;
(2) The name and location of the historic property subject to review;
(3) The statute under which review is requested; and
(4) Any other information requested in writing by the board or office.
Source: 21 SDR 50, effective September 21, 1994.
General Authority:SDCL 1-19A-5, 1-19A-11, 1-19A-13.5, 1-19A-27, 1-19A-29.
Law Implemented:SDCL 1-19A-5, 1-19A-11.1, 1-19A-13.1, 1-19A-20 to 1-19A-23, 1-19A-25 to 1-19A-26.
24:52:13:02. Requests for information. At any time in the course of a project review the board or the office may request information from an applicant necessary for review of the project.
Source: 21 SDR 50, effective September 21, 1994.
General Authority:SDCL 1-19A-5, 1-19A-11, 1-19A-13.5, 1-19A-29.
24:52:13:03. Project review -- Grounds for denial of application. The board and the office shall consider information provided in applications and other information against standards and requirements specified in SDCL chapter 1-19A and in chapters 24:52:00, 24:52:06, and 24:52:07. The board or the office may deny applications or requests based on the following:
(1) Failure to meet the standards, or rules, or requirements of the board or office in this article or the rules in this chapter;
(2) Failure to provide information requested by the board or the office;
(3) Failure to demonstrate good faith effort to comply with statute or rule.
Source: 21 SDR 50, effective September 21, 1994.
General Authority:SDCL 1-19A-5, 1-19A-11, 1-19A-13.5, 1-19A-29.