70:10:01:07. Priority for consideration of application
approval. In determining whether to grant or deny a permit application, the
department shall consider applications in the following order:
(1) From any utility whose
facilities are not located over, under, or along any public ground, street,
alley, or highway under the jurisdiction of the department but are displaced as
a result of a highway construction project;
(2) From any utility whose
facilities are located over, under, or along any public ground, street, alley,
or highway under the jurisdiction of the department, and are displaced as a
result of a highway construction project; and
(3) From any other utility.
The department shall approve or deny
all timely applications submitted by utilities that satisfy the requirements of
subdivision (1) prior to considering any applications from utilities that meet
the requirements of subdivision (2). The department shall approve or deny all
timely applications submitted by utilities that satisfy the requirements of
subdivision (2) prior to considering any applications that meet the
requirements of subdivision (3).
Source:
32 SDR 32, effective August 30, 2005.
General
Authority: SDCL 31-19-1.1.
Law
Implemented: SDCL 31-19-1.1.