20:10:36:06. Application fees. The public utility shall
require a non-refundable application processing fee for each application. The
amount of the fee is dependent upon the review tier requested in the
application and is intended to cover reasonable costs for processing, minor
study, and evaluation of the application. Any application requiring a detailed
study and engineering evaluation may incur costs that are not covered by the
application fee. Before any costs above the application fee are assessed, the
applicant must authorize the public utility to continue by assuming
responsibility for the additional costs, or the application will be considered
withdrawn and the original application fee forfeited.
The application fees are as follows:
(1) Tier 1: $50;
(2) Tier 2: $50 plus $1 per kilowatt of rated
generation output up to a maximum of $500;
(3) Tier 3: $100 plus $2 per kilowatt of rated
generation output up to a maximum of $1,000; and
(4) Tier 4: $100 plus $2 per kilowatt of rated
generation output up to a maximum of $1,000.
If an application fails to receive approval at one review
tier and makes a subsequent application for the same facility at a different
tier within the time frame for preserving the queue position, the original
application fee and any other fees paid in conjunction with the original
application will be applied to the fees for the updated application. By mutual
agreement, the review process can move directly to the next tier without filing
a separate formal application.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.