20:10:36:09. Aggregating multiple generators. If the
interconnection request is for a small generator facility that includes
multiple small generator facilities at a site for which the applicant seeks a
single point of interconnection, the application shall be evaluated for the
purpose of the interconnection on the basis of the aggregate electric nameplate
capacity of the multiple small generator facilities.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.