74:55:01:53.01. Excursions -- Controlled. An excursion is
controlled if it can be demonstrated through water quality and ground water
gradient or if applicable, pressure measurements, that recovery fluid in
unauthorized areas is declining.
If the excursion is controlled, but
the control parameters have not been restored to values consistent with local
baseline water quality within 60 days following confirmation of the excursion,
the operator shall submit, within 90 days following confirmation of the excursion,
a plan and schedule, for approval by the secretary, for bringing the well or
wells off excursion. The plan and schedule can be submitted as part of the
excursion report required every two weeks in § 74:55:01:53.
Clean up is considered accomplished if
the water quality in the affected monitor wells has been restored to values
consistent with local baseline water quality and the restoration is confirmed
by three consecutive weekly samples. The secretary may determine that clean up
is not necessary if the operator demonstrates that the change in water quality
is not due to the presence of recovery fluids.