20:10:36:07. Term of interconnection. Interconnection of
a small generator facility is considered to be in effect for a period of up to
20 years at the interconnection customer's option, unless terminated earlier by
the default or voluntary termination by the interconnection customer or by
action of the commission. Any interconnection agreement entered into before the
effective date of this rule shall remain in effect until the term of the
agreement expires.
Source: 35 SDR
305, effective July 1, 2009.
General Authority:
SDCL 49-34A-27, 49-34A-93.
Law Implemented:
SDCL 49-34A-27, 49-34A-93.