MyLRC +
Administrative Rules
Rule 70:13:01:04 Application and approval periods.

          70:13:01:04.  Application and approval periods. An LPA shall submit any applications for bridge preservation, rehabilitation, and replacement grants no later than January 2 of each year, and the commission shall consider those applications by April 30 of each year. An LPA shall submit any applications for preliminary engineering grants no later than August 1 of each year, and the commission shall consider those applications by October 30 of each year.

 

          Source: 42 SDR 52, effective October 13, 2015; 43 SDR 57, effective October 17, 2016; 44 SDR 42, effective September 11, 2017.

          General Authority: SDCL 32-11-39.

          Law Implemented: SDCL 32-11-38, 32-11-39.